Modular Ceramic Membrane Water Treatment Plant
Client – Bournemouth Water
Major upgrade at Alderney WTW with advanced modular ozonated ceramic membrane technology.
Introduction
For over a century, Alderney Water Treatment Works (WTW) in Bournemouth has been relied upon to provide safe, clean drinking water to the local community. As demands on the water network continued to grow, and the effects of climate change became more pressing, a major transformation of this essential facility was identified as a requirement. The large-scale infrastructure project is a key part of Bournemouth Water’s investment programme to modernise the water system, future-proof it against a changing climate and minimise the impact on the environment. The overall project goal is summarised in Bournemouth Water’s Strategic Objectives statement:
“Delivery of a world class drinking water supply solution for the supply network serving BW customers, providing excellent water quality and long-term water supply security for the region.”
RSE is proud to be supporting this transformation through the design, manufacture, installation, commissioning and optimisation of a new modular water treatment plant that combines advanced technology with a sustainable off-site modular construction approach.
RSE was contracted to deliver the new 84ML/day ceramic membrane treatment plant at Alderney, deploying a range of RSE Standard Product Off-Site Modular Solutions. This included the integration of ozone dosing upfront of the PWNT CeraMac® 37 ceramic membrane system which allows the plant to operate at a higher flux, with less chemical cleaning required, and within a smaller overall plant footprint. The completed plant will deliver high quality water, whilst enhancing the overall efficiency and resilience of the site, and providing a barrier to Cryptosporidium.
This project is not solely centered around technology upgrades. It also serves as a showcase of RSE’s strengths in standardised modular construction, environmental awareness, and seamless project delivery. The Alderney upgrade demonstrates what is possible when innovation, collaborative planning, and sustainability are prioritised from the outset.
Delivering a Smarter Approach
From day one, RSE recognised that a modular construction approach would offer the best path to meet both the technical and environmental goals of the project. By fabricating and assembling major elements of the new plant off-site, RSE enabled civil works to proceed in parallel, which significantly shortened the delivery timeline (12 month reduction) and minimised disruption at the live treatment site, and to the nearby residents.
While civil engineering was underway on location, modular units were being built at RSE’s manufacturing facilities across the UK. Meanwhile, the CeraMac® systems were fabricated in Italy and the Netherlands. By progressing all aspects in tandem, the RSE build was able to be delivered at an unmatched pace.
Thanks to our Standard Product range, RSE was able to procure all long-lead items immediately after order placement, and release work packs to our Production facilities to allow commencement of fabrication activities exactly when required. RSE’s ability to leverage simultaneous working (not only between on-site and off-site activities, but also between our own work packages and subcontractors), enabled us to significantly condense the programme for Bournemouth Water and offer total surety on programme dates, all whilst upholding our high standards of quality and safety”.
Jamie Miller (Senior Project Manager – Treatment Solutions)
Achieving Major Project Milestones
RSE started work in April 2023, focusing first on critical path design and long-lead procurement items. Full-scale fabrication works started within five months, followed by off-site modular assembly starting in early 2024. The first modular units arrived at the site in October 2024, already commissioned off-site, ready for integration. The final unit was delivered in December 2024, marking the end of the off-site delivery phase.
In total, 70 modular units were safely transported to site and reassembled across just eight weeks. With the commissioning phase scheduled for completion in 2025, the RSE contract will be delivered both on time and to specification. This will stand as the largest modular-built ceramic membrane plant in the UK, and was completed in half the time of a conventional build.
Precision Planning with Digital Tools
The scale of this project required careful and coordinated logistics. RSE’s in-house Building Information Modelling (BIM) team developed a detailed 4D animation using Autodesk Construction Cloud models, enabling every stakeholder to visualise and understand the delivery sequence in real time.
This step-by-step animation mapped out how each modular unit would be delivered and reassembled, ensuring a smooth process for the installation teams, hauliers, and onsite crews.
The digital planning also provided the client full visibility into every stage of the build.
Built for Performance and Sustainability
Environmental efficiency is a core focus throughout the Alderney upgrade. Rather than demolishing and rebuilding the facility from scratch, the project team have retained key parts of the existing infrastructure and integrated new treatment processes within them. This approach has reduced carbon emissions and environmental impact.
The RSE modular approach brought additional benefits by reducing time on site, minimising vehicle traffic, and cutting construction waste. The use of ceramic membranes also contributes to long-term operational savings, thanks to their durability and lower energy requirements.
Recognition Through Innovation: The King’s Award
In June 2025, RSE was honoured with the King’s Award for Enterprise, the highest accolade available to UK businesses, in recognition of our contribution to innovation in the water industry. The award specifically acknowledged the groundbreaking work behind our off-site build methodology and our development of the modular m-CTU product, both of which were instrumental to the successful delivery of the Alderney WTW project.
The Alderney upgrade exemplifies the very innovation that the award celebrates. By embracing a modular, factory-built approach and integrating advanced treatment processes into standardised units, the project delivered significant gains in efficiency, quality, and sustainability. These same principles formed the foundation of King’s Award submission and ultimately secured this national recognition.
The success of the Alderney project stands as a real-world demonstration of why RSE received this honour, showcasing how innovation, when applied with purpose, can help transform the water industry and set new standards for delivery.
Proven Delivery Model
The Alderney project showcases the reliability of RSE’s integrated delivery model. With in-house capabilities across design, automation, and installation, RSE are able to control every aspect of delivery with precision.
Supporting the successful outcomes were:
- More than 40,000 square meters of factory-controlled production space.
- Automated manufacturing processes with built-in assurance.
- A national network of 26 facilities supporting regional mobilistation.
- Self-delivery across electrical, mechanical, and control disciplines.
- 4D modelling and real-time delivery tracking
- Standardised, repeatable product solutions tailored to each project
- Dedicated teams focused on safety, compliance, and technical excellence.
This integrated approach allows RSE to meet commitments with certainty, delivering a high-quality product, within the agreed budget and schedule.
Summary
The upgrade at Alderney WTW stands as a benchmark for modular delivery in the water industry. It demonstrates how innovative thinking and modern construction methods can respond to the challenges facing water networks today, while also laying the foundation for more sustainable infrastructure in the future. It demonstrates what can be achieved in partnership with innovative clients who are committed to providing high levels of engagement and collaboration, to secure best outcomes for their end customers.
From early design through the final commissioning, RSE’s team are delivering a complex, high-value project with precision, speed, and care. The successes at Alderney highlights not only our technical capabilities but also our ongoing commitment to supporting the UK’s water industry with solutions that are smarter, faster, and cleaner. It is testament to Bournemouth Water and the respective teams who have underpinned the delivery of the overall project.
Want to Know More?
To find out more about how our modular approach speeds up delivery, reduces embodied carbon and supports the secure and sustainable growth of water infrastructure, click on the button below and please fill in the form. We’ll get back to you shortly.