The LMB® Is a Low Carbon Direct Replacement for Industry-Standard Enclosures.
The LMB® is Part of RSE’s m-EcoBuilding® Product Line, Characterised by Industry-Leading and Modular Offsite Build Capabilities, Enabling Plug and-Play Options Whilst Contributing to Significant Carbon Savings.
Precision Design & Engineering Throughout
The LMB® is designed and manufactured using a specialised integrated CAD/CAM software solution to create models for use with precision CNC machinery.
This approach ensures a high level of accuracy, quick turnaround, reductions in fabrication costs, and improvements in lead times for clients.
The LMB® steelwork frames for standard products are designed to Eurocodes Annex structural design standard (Eurocode 3), ensuring conformance, safety, and durability regardless of its location within the UK.
Site specific LMB® frames are also designed to withstand local wind and snow loads to ensure efficient use of materials.
Alternative to GRP and Conventional Steel Storage
Fabricated from steel framing, generated by the FRAMECAD TF550H roll forming machine using light gauge galvanised steel coil, LMB®s offer a suitable alternative to GRP and conventional steel enclosures or kiosks.
The LMB® confidently meets and exceeds the 25-year design life of plastic alternatives, underlining its exceptional quality.
Precision Engineering
The LMB® combines innovative engineering solutions and fabrication, with an emphasis on modular and offsite construction to reduce lead times.
The 3D CAD Software utilised in conjunction with the FRAMECAD TF550H enables the roll-forming accuracy down to +/- 0.1mm and build tolerances for the LMB® frame structure of +/- 3mm.
Environmental Impact
This innovative approach using alternative and sustainable materials maximises the reduction in embodied carbon, whilst maintaining high-quality standards.
Key Features
LMB® Applications
An LMB® can be a suitable option for a range of applications
Standard sizes available:
3m (width) x 3m (length) x 2.7m (height)
4m (width) x 3m (length) x 2.7m (height)
6m (width) x 3m (length) x 2.7m (height)
8m (width) x 3m (length) x 2.7m (height)
Bespoke sizes available on request in line with transportation constraints
80%
LMB® Reduces carbon emissions by up to 80% (kgCO2 equiv vs GRP)
100%
LMB® is 100% recyclable at end of life
Tiree WTW
An LMB® was utilised for a new pumping station as part of CWBT replacement.
- January – March 2023: LMB® was designed with a base frame.
- April – June 2023: Fabrication including fit out with building services in RSE’s Muir of Ord facilities.
- June – August 2023: Fitted out with equipment and commissioned.
- August 2023: Shipped to site, transported by road as a modular unit from Muir of Ord to Oban, then by ferry to Tiree.
- Project Completion: The project achieved an embodied carbon reduction of 49% compared to a standard unit.
Stoneybridge WTW
An LMB® was utilised as a chemical store, required as part of an upgrade to an existing water treatment works.
- August – September 2023: LMB® was designed with an elevated floor frame.
- September – November 2023: Fabrication including fit out with building services in RSE’s Muir of Ord facilities.
- October 2023: Bund manufacture completed by RSE Chemical Dosing division located in Dalgety Bay.
- November 2023: Shipped to site, transported by road as a modular unit from Muir of Ord to Skye, then by ferry to Uist.
- Project Completion: The project achieved an embodied carbon reduction of 81% compared to a standard unit.
”RSE addresses the challenges facing the UK water sector by offering pioneering products and solutions like the LMB® that will have real environmental benefits and represent a significant step towards a greener and more efficient water industry.
Stephen SlessorRSE Chief Executive Officer
Tiree WTW – RSE Deliver Vital Upgrades to Water Treatment Works (Non-standard Product)
Downloads
LMB® Fact Sheet
LMB® Product Document
LMB® Material Certification
Direct enquiries to LMB@onerse.com
Enquire Now
Speak to Our Team
Learn more about our business, products or services by completing the form, or alternatively fill in our public feedback form here.